Chappaqua Downtown Revitalization – July 22, 2019

As part of the traffic light installation, over the next 2 weeks, they will start installing the 5 pedestrian poles at the King/Greeley intersection. The first 2 pedestrian poles will be installed at the corners of Starbucks & North Country Sotheby’s. The poles will allow pedestrians to press a button to change the walk signal to green. We will be excavating for the pedestrian pole footings, installing rebar & then concrete for the pole footings. We will also be excavating & installing electrical conduits.

As far as upper King to North Greeley (Waka side), this week they will finish installing the granite curb and then place concrete in front of the curb.

As far as upper King from South Greeley to Senter Street (Family Britches side), they will finish installing the granite curb & then place concrete in front of the curb. They will excavate & grade for the sidewalk. They will install irrigation, conduits & light pole footings. Next week they will pour the sidewalks.

By the historical society, they will continue to excavate & install granite curb.