Here is the Master Plan Project Schedule:

   Phase Start Date Completed
1 Outreach and Education Process (PACE LULC) March 2014 July 2014
2 Master Plan Steering Committee and Workgroup (SWOT) June 2014 August 2014
3 Synthesis of Outreach Process /Identification of Goals and Objectives/Identification of Strategies/Changes from 1989  October 2014 December 2014
4 Public Engagement Regarding the Goals and Objectives of the Master Plan Update January 2015 February 2015
5 Compile Draft Document February 2015  April 2015
6 Environmental Review of Draft Document April 2015  June 2015 
7 Public Hearing on Draft Master Plan June 2015  June 2015
8 Revisions to Draft Master Plan Based On Comments Received July 2015  July 2015 
9 Public Hearings on Final Draft Master Plan  September 2015 September 2015 
10 Town Board Consideration of Adoption of Master Plan October 2015 November 2015